Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

In January 2 0 2 2 , Chen recognized the potential opportunity to invest in a solar power system. A contractor submitted two independent proposals

In January 2022, Chen recognized the potential opportunity to invest in a solar power system. A contractor submitted two independent proposals for solar systems: one for the 100kW, the other for the 230kW. The solar panels for the 100kW system would require 7,000 square feet (650 square metres) of roof space, while the solar panels for the 230kW system would require 15,000 square feet (1,400 square metres). The proposals suggested installing the 100kW system on the main factory roof and the 230kW system on the main factory roof with its excess panels on the finished goods warehouse built primarily to support storage of finished goods inventory (see Exhibit 5).
Both systems consisted of solar panels, mounting equipment, inverters, wiring, and labour required for installation. And once parts were acquired, installation would take six weeks. The contractor would purchase and import the parts and equipment then install in 2022, with the system becoming operational around the start of 2023.
at pre-tax cost of debt of percent. The bass realment tens were to be mgual to the sai os we yater The corporate tax rate was 25 per cent. Tax rules in Jamaica depreciated solar equipment on a straight-line basis over eight years with 0 per cent initial allowances in the year of purchase. Given the highly customized nature of the solar power system installation, neither system was expected to have a salvage value.
100-Kilowatt System
The 100kW system's 220 solar panels, two inverters, and all necessary mounting equipment would cost US$134,757 to purchase and import to Jamaica net of GCT exemptions. The fee to install the roof racking, solar panels, and electrical equipment to carry power from the roof of JMF's main factory building into the factory's electrical system would be US$61,216. The 100kW system would be capable of selling electricity back to the grid, which would incur an additional $400,000 for licensing and the professional electrical engineering fees required to approve the additional equipment installation required to facilitate net billing.
The usage charge savings for the 100kW system were projected to be $563,000 per month in 2023. Due to solar panel degradation, the usage charge savings produced would decrease linearly by 3 per cent of the original 2023 savings every year for the project's duration. Demand charge savings would not begin until the following year with $2,140,000 of savings per year from decreased peak power usage. Like the usage charge savings, solar panel degradation would also cause the demand charge savings to decrease linearly by 3 per cent of the original 2024 value per year. Foreign exchange savings were expected to be $50,000 in 2023 and increase by 2 per cent each year over the life of the project.
JMF would also generate revenue through selling excess power to the utility provider. Given that the solar power system could generate excess power approximately two days per week, revenue generated through net billing for each year would be two-fifths multiplied by the electricity usage savings and multiplied by a factor of one-fifth. This total accounted for the difference in the price that JMF initially purchased electricity versus the price that JPS repurchased electricity. System maintenance would be $400,000 per year beginning in 2023 and increase by 1 per cent per year, and insurance would cost $380,000 per year for the project's duration.
The 230kw system would require 510 solar panels each capable of producing 0.445kW as well as two inverters for a net cost of US$196,979. Installation of the panels and all the necessary electrical equipment would cost US$75,761.
Although the 230kW system was much larger than the 100kW system, the 230kW system was strategically oversized relative to JMF's energy usage to capture sunlight throughout parts of the day when the panels experienced sub optimal sunlight such as early mornings or late evenings (see Exhibit 6). As a result, the 230kW system would be capable of saving $726,000 per month in usage charges in 2023, while the demand charge savings would be $2,420,000 per year beginning in 2024. However, the solar panels in the 230kW system would degrade at a similar rate to the 100kW system, and foreign exchange savings were expected to be $70,000 in 2023 and increase at a similar rate as the 100kW system. The maintenance and insurance costs would be higher on the larger system costing the company $960,000 per year in 2023 and increasing at a rate of 1 per cent per year and $728,000 per year, respectively, for the life of the system. Using NPV analysis, evaluate the financial feasibility of the two investment opportunities.
Perform sensitivity analysis with 7% growth rate for foreign exchange savings.
What would be the qualitative aspects of investment opportunities Nicholas need to consider?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

College Accounting Chapters 1-30

Authors: John Price, M. David Haddock, Michael Farina

15th edition

1259994975, 125999497X, 1259631117, 978-1259631115

Students also viewed these Accounting questions