Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

in January 2 0 2 2 , Nicholas Chen had to decide whether to invest in one of the two solar power systems to reduce

in January 2022, Nicholas Chen had to decide whether to invest in one of the two solar power systems to reduce the energy costs of Jamaican Macaroni Limiteds (JMF) factory. If Chen decided to proceed with one of the two solar systems, he also needed to decide whether to accept the contractors proposed installation on the main factory roof or another JMF building. Chens decision was primarily driven by increasing electricity costs, which were affecting the companys profitability. The economic conditions favored investment in a solar power system and financing had been secured. Thus, Chen had three main options: (1) purchase a 100kW solar power system and generate some of the energy JMF used while also selling back electricity to the grid when the factory was not operating; (2) purchase a 230kW system, which would produce more energy but due to regulatory restrictions would not sell electricity back to the grid: or (3) reject both options and face rising energy costs. Students are expected to perform a net present value (NPV) analysis to assess the viability of each alternative, including where to install the system in addition to assessing the economic and industry trends. Overall alignment with JMFs business philosophy should also be considered. 100-Kilowatt SystemThe 100kW systems 220 solar panels, two inverters, and all necessary mounting equipment would cost US$134,757 to purchase and import to Jamaica net of GCT exemptions. The fee to install the roof racking, solar panels, and electrical equipment to carry power from the roof of JMFs main factory building into the factorys electrical system would be US$61,216. The 100kW system would be capable of selling electricity back to the grid, which would incur an additional $400,000 for licensing and the professional electrical engineering fees required to approve the additional equipment installation required to facilitate net billing.The usage charge savings for the 100kW system were projected to be $563,000 per month in 2023. Due to solar panel degradation, the usage charge savings produced would decrease linearly by 3 per cent of the original 2023 savings every year for the project's duration. Demand charge savings would not begin until the following year with $2,140,000 of savings per year from decreased peak power usage. Like the usage charge savings, solar panel degradation would also cause the demand charge savings to decrease linearly by 3 per cent of the original 2024 value per year. Foreign exchange savings were expected to be $50,000 in 2023 and increase by 2 per cent each year over the life of the project.JMF would also generate revenue through selling excess power to the utility provider. Given that the solar power system could generate excess power approximately two days per week, revenue generated through net billing for each year would be two-fifths multiplied by the electricity usage savings and multiplied by a factor of one-fifth. This total accounted for the difference in the price that JMF initially purchased electricity versus the price that JPS repurchased electricity. System maintenance would be $400,000 per year beginning in 2023 and increase by 1 per cent per year, and insurance would cost $380,000 per year for the projects duration.230-Kilowatt SystemThe 230kw system would require 510 solar panels each capable of producing 0.445kW as well as two inverters for a net cost of US$196,979. Installation of the panels and all the necessary electrical equipment would cost US$75,761.Although the 230kW system was much larger than the 100kW system, the 230kW system was strategically oversized relative to JMFs energy usage to capture sunlight throughout parts of the day when the panels experienced sub optimal sunlight such as early mornings or late evenings (see Exhibit 6). As a result, the 230kW system would be capable of saving $726,000 per month in usage charges in 2023, while the demand charge savings would be $2,420,000 per year beginning in 2024. However, the solar panels in the 230kW system would degrade at a similar rate to the 100kW system, and foreign exchange savings were expected to be $70,000 in 2023 and increase at a similar rate as the 100kW system. The maintenance and insurance costs would be higher on the larger system costing the company $960,000 per year in 2023 and increasing at a rate of 1 per cent per year and $728,000 per year, respectively, for the life of the system.1. Calculate the Total Initial Invesment , Total Cash Inflows And outflow, NPV, IRRR, payback2. Perform a complete qualitative analysis of the investment opportunities Chen is considering. Analyze the pros and cons of each opportunity.3. Quantitatively evaluate the financial viability of the two investment opportunities. Consider the IRR, NPV, and payback of each investment opportunity. Also evaluate the effect of uncertainty of the foreign exchange rate on the investment decision.4. Summarize your analysis and recommend a decision for Chen to invest in one or none of the two solar power projects of Jamaica Macaroni Factory on the basis of your quantitative and qualitative analysis

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Private Debt Yield Safety And The Emergence Of Alternative Lending

Authors: Stephen L. Nesbitt

2nd Edition

1119944392, 978-1119944393

More Books

Students also viewed these Finance questions