Question
1 Approved Answer
In making an estimate of the most pessimistic time for an activity, a manager deliberately estimates this time too high (i.e., longer than it should
In making an estimate of the most pessimistic time for an activity, a manager deliberately estimates this time too high (i.e., longer than it should be). What is the result of this action, assuming the beta distribution is being used to make time estimates?
Select one:
A. The expected time for this activity will be larger than it should be.
B. The variance of the activity will be smaller than it should be.
C. The beta distribution will be symmetric around its mean.
D. The most likely time for this activity will be larger than it should be.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started