Sid Davidson is the personnel director of Babson and Willcount, a company that specializes in consulting and research. One of the training programs that Sid is considering for the middle-level managers of Babson and Willcount is leadership training. Sid has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities and immediate predecessors appear in the following table:
______________________________________________________________________________________
ActivityImmediate Predecessors
______________________________________________________________________________________
A____
B____
C____
DB
EA,D
FC
GE,F
Develop a network for this program.
That was the first problem. This is the oneI need an answer to.
11-13: Sid Davidson was able to determine the activity times for the leadership training program. He would like to determine the total project completion time and thecritical path. The activity times appear in the following table:
__________________________________________________________________________________
ACTIVITY TIME (DAYS)
A 2
B5
C 1
D10
E3
F 6
G8
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started