In project management, the difference between CPM and PERT is that Group of answer choices CPM is used when the order of activities are known,
In project management, the difference between CPM and PERT is that
Group of answer choices
CPM is used when the order of activities are known, and PERT is used when the order of activities is uncertain
PERT is used when activity times are known, and CPM is used when activity times are uncertain
CPM is used when activity times are known, and PERT is used when activity times are uncertain
PERT is used when the order of activities are known, and CPM is used when the order of activities is uncertain
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started