In September, Pinata Company reports 18,600 actual direct labor hours, and it incurs $120,540 of manufacturing overhead costs. Standard hours allowed for the work done
In September, Pinata Company reports 18,600 actual direct labor hours, and it incurs $120,540 of manufacturing overhead costs. Standard hours allowed for the work done is 22,200 hours. The predetermined overhead rate is $5.75 per direct labor hour. Compute the total overhead variance.