In the case where resources are assigned for the duration of the project rather than rolled off and rolled on as needed, compared to the
In the case where resources are assigned for the duration of the project rather than rolled off and rolled on as needed, compared to the non-leveled plan resource leveling will A. increase utilization of the resources assigned to the project B. increase expenses related to hiring/firing for the project C. increase variability in project cash flow for the project D. All of the above