In the context of critical path analysis (CPA), answer the following questions. Illustrate your answers with practical examples. i. What is the critical path?
In the context of critical path analysis (CPA), answer the following questions. Illustrate your answers with practical examples. i. What is the critical path? [30 marks] II. Two activities in the critical path are delayed by, respectively, 2 and 3 days. What are the [30 marks] implications of that in the project? iii. A given path of activities in a project is 10 days long, i.e. the sum of the expected times to complete each of the activities (durations) belonging to this path is 10 days. What can be [20 marks] said about the completion time (duration) of the entire project? iv. Explain what 'crashing' means and how a project manager would approach the decision around what activities to 'crash' [20 marks]
Step by Step Solution
There are 3 Steps involved in it
Step: 1
1 The critical path in critical path analysis CPA is the longest sequence of dependent activities that must be completed on time for the entire projec...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started