Answered step by step
Verified Expert Solution
Question
1 Approved Answer
In the following example of a project schedule, the total duration is listed as 67 days; however, there are 117 calendar days between January 1st
In the following example of a project schedule, the total duration is listed as 67 days; however, there are 117 calendar days between January 1st and April 28th. Why does the project's "Duration" column not exactly match the number of calendar days between the scheduled start and finish dates? Project Schedule Duration Question 13 options: The duration includes additional days for contingencies The duration only includes production days The duration only counts days on the critical path The duration only counts the number of working days
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started