Question

1 Approved Answer

In the following MRP planning schedule for item J, indicate the correct net requirements, planned-order receipts, and planned-order releases to meet the gross requirements. Lead

image text in transcribed
In the following MRP planning schedule for item J, indicate the correct net requirements, planned-order receipts, and planned-order releases to meet the gross requirements. Lead time is one week. Note: Leave the cells blank, whenever zero (0) is required