In the following network, manually level your resources so that you may not use more than 7 laborers per day at any time. Activity Predecessor
In the following network, manually level your resources so that you may not use more than 7 laborers per day at any time.
Activity | Predecessor | Duration (Days) | Labors |
A | - | 2 | 4 |
B | - | 3 | 2 |
C | A | 1 | 6 |
D | A, B | 3 | 3 |
E | C, D | 2 | 1 |
The company can provide only 7 labors per day. Thus
1. Draw the network.
2. Allocate resources.
3. Level the resources.