Question

1 Approved Answer

In the following table the activities, the duration and the sequencing relations of a project. The critical path is AEJKLN and it duration is 37

In the following table the activities, the duration and the sequencing relations of a project. The critical path is AEJKLN and it duration is 37 days.

Answer with Right or Wrong in the following:

a) If the duration of A increases by two days, the duration of the project will be increased by the same time.

b) If the duration of B increases by one day, the duration of the project will be increased.

c) The available time for executing E is 10 days.

d) The available time for executing H is 8 days.

e) The duration of L does not impact the start time of N.

Activity Previous activity Duration in days
A - 3
B - 4
C - 6
D B 3
E A 9
F A 7
G B 4
H C,D 5
I C,D 4
J E 3
K F,G,H 6
L F,G,H 7
M I,J,K 6
N J,K

9

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Effective small business management An Entrepreneurial Approach

Authors: Norman M. Scarborough

10th Edition

132157462, 978-0132157469

More Books

Students also viewed these General Management questions

Question

2 How does the caravan market appear to segment?

Answered: 1 week ago