Question
In the following table the activities, the duration and the sequencing relations of a project. The critical path is AEJKLN and it duration is 37
In the following table the activities, the duration and the sequencing relations of a project. The critical path is AEJKLN and it duration is 37 days.
Answer with Right or Wrong in the following:
a) If the duration of A increases by two days, the duration of the project will be increased by the same time.
b) If the duration of B increases by one day, the duration of the project will be increased.
c) The available time for executing E is 10 days.
d) The available time for executing H is 8 days.
e) The duration of L does not impact the start time of N.
Activity | Previous activity | Duration in days |
A | - | 3 |
B | - | 4 |
C | - | 6 |
D | B | 3 |
E | A | 9 |
F | A | 7 |
G | B | 4 |
H | C,D | 5 |
I | C,D | 4 |
J | E | 3 |
K | F,G,H | 6 |
L | F,G,H | 7 |
M | I,J,K | 6 |
N | J,K | 9
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started