In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company
In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working: K Immediate Predecessor(s) Time (days) Activity A 3 B 4 6 6 4 4 6 9 Carl's team should be able to complete the project in days. Critical path activities for Carl's project are A-C-F-H A-B-E-H A-B-D-G E F G H A A B B C D E, F