In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Processors Time (Days) A

In the following table the activities with their precedence sequence and expected time (days) are listed for a project:

Activity Immediate Processors Time (Days)
A - 8
B - 2
C - 8
D B 10
E A,D 4
F C 6
G E,F 10
  1. Draw an AON Diagram
  2. The Critical Path(s) _______________.
  3. The Project Length _______________ Days.
  4. What is the lack time for each activity.
Activity Slack
A
B
C
D
E
F
G

Is somebody would solve this for me I would greatly appreciate it! Thank you in advance!

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Management

Authors: Robbins, DeCenzo, Coulter

7th Edition

132996855, 0-13-610982-9 , 9780132996853, 978-0-13-61098, 978-0136109822

More Books

Students also viewed these General Management questions