In the following WBS the total project cost is estimated to be $1,200,000. Use this WBS to answer questions 18 through 21. Refer to the
In the following WBS the total project cost is estimated to be $1,200,000. Use this WBS to answer questions 18 through 21.
Refer to the House Construction Work Breakdown Structure and calculate the estimated cost for the 'Internal work' sub deliverable.
Select one:
A.
$360,000
B.
$380,000
C.
$400,000
D.
$420,000
Question 19
Refer to the House Construction Work Breakdown Structure and calculate estimated cost for the 'Roofing' deliverable.
Select one:
A.
$120,000
B.
$240,000
C.
$360,000
D.
$480,000
In the House Construction Work Breakdown Structure which of the following choices represent a work package?
Select one:
A.
Foundation
B.
Internal work
C.
External work
D.
HVAC
Question 21
In the House Construction WBS which of the following choices could represent a control account?
Select one:
A.
IT and security
B.
Excavation
C.
Foundation
D.
Building finishes
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started