Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

In the table below, job definitions, precedence relations, resource requirements, unit crash costs and crash limits for a chemical installation scheduling project are given. Daily

In the table below, job definitions, precedence relations, resource requirements, unit crash costs and crash limits for a chemical installation scheduling project are given. Daily working hours are 7:30 to 17:30 with a lunch break during 12:00-13:00. The chemical installation team gives a break on weekends and national and Muslim religious holidays. The project will start on April 17,2023 at 7.30 hrs.| Job No 1234567891011121314151617181920 Job Clear site Excavation and foundations Install support steelwork Install stairways Install platforms Install handrails and platform angles Install equipment Calibrate equipment Install prefabricated ductwork Install prefabricated process pipework Make pipework connections to equipment Install prefabricated service pipework Make service pipework connections to equipment Install instrumentation Make instrument connections to equipment Install electrical apparatus Make electrical connections to equipment Lay equipment Lay pipework Lay ductwork Testing equipment 212223*Work in progress. Painting Clean up Budgeted Actual Duration Duration (days)(days)4381038747221047736154961013689124875620116874715 ww 76 ww -- Completeness (%)10010010010010010010010010010010010010010010075*045*35*01000 Budgeted 10081890132366142561323109211705733945716388110586047531358 Cost (TL)18946790273032921638261516203825 Actual 106916301524691456715951352148256391095318398025605049931268203519601598 W -- ASSIGNMENT PART 21) Determine the date of monitoring by assuming that the activities in progress occur simultaneously. 2) Calculate and give interpretations with regard to the status of the project using the accounting variance, the cost variance, the schedule variance, the schedule performance index, the cost performance index, and the expected performance index. Assume costs are incurred at the end of activities. 3) Considering the completed activities, as well as those that are not completed yet, state the expected project duration. In the table below, job definitions, precedence relations, resource requirements, unit crash costs and crash limits for a chemical installation scheduling project are given. Daily working hours are 7:30 to \(17: 30\) with a lunch break during 12:00-13:00. The chemical installation team gives a break on weekends and national and Muslim religious holidays. The project will start on April i7 onz at 7 an hre I - Work in progress. ASSIGNMENT PART 21) Determine the date of monitoring by assuming that the activities in progress occur simultaneously. 2) Calculate and give interpretations with regard to the status of the project using the accounting variance, the cost variance, the schedule variance, the schedule performance index, the cost performance index, and the expected performance index. Assume costs are incurred at the end of activities. 3) Considering the completed activities, as well as those that are not completed yet, state the expected project duration.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Social Media Management

Authors: Ben Shields

1st Edition

019029633X, 978-0190296339

More Books

Students also viewed these General Management questions

Question

Describe the use of tests in the selection process.

Answered: 1 week ago

Question

Explain pre-employment screening and background checks.

Answered: 1 week ago