In traditional just in time philosophy the value added time is 12, the non value added time is 718 which gives you the total lead
In traditional just in time philosophy the value added time is 12, the non value added time is 718 which gives you the total lead time to be 730. What is the value-aded ratio as a percent? I have gotten all of these answers which are correct bt somehow I can not get the correct percent ratio. Any help would be appreciated! Than you