Incomplete manufacturing cost data for Horizon Company for 2020 are presented as follows for four different situations. (a) New attempt is in progress. Some of
Incomplete manufacturing cost data for Horizon Company for 2020 are presented as follows for four different situations.
(a)
New attempt is in progress. Some of the new entries may impact the last attempt grading.Your answer is incorrect.
Indicate the missing amount for each letter.
Direct Materials Used | Direct Labor Used | Manufacturing Overhead | Total Manufacturing Costs | Work in Process 1/1 | Work in Process 12/31 | Cost of Goods Manufactured | |||||||||||||||
(1) | $118,400 | $142,000 | $92,000 | $ | (a) | $34,500 | $ | (b) | $361,300 | ||||||||||||
(2) | (c) | 204,000 | 135,000 | 451,900 | (d) | 44,500 | 472,400 | ||||||||||||||
(3) | 83,300 | 101,300 | (e) | 267,700 | 62,000 | 82,300 | (f) | ||||||||||||||
(4) | 75,900 | (g) | 80,200 | 289,900 | 49,100 | (h) | 274,800 |
Direct Materials Used | Direct Labor Used | Manufacturing Overhead | Total Manufacturing Costs | Work in Process 1/1 | Work in Process 12/31 | Cost of Goods Manufactured | |||||||||||||||
(1) | $118,400 | $142,000 | $92,000 | $ | (a) | $34,500 | $ | (b) | $361,300 | ||||||||||||
(2) | (c) | 204,000 | 135,000 | 451,900 | (d) | 44,500 | 472,400 | ||||||||||||||
(3) | 83,300 | 101,300 | (e) | 267,700 | 62,000 | 82,300 | (f) | ||||||||||||||
(4) | 75,900 | (g) | 80,200 | 289,900 | 49,100 | (h) | 274,800 |
This is all the information provided missing numbers with numbered boxes is what they are asking me to solve for ?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started