Question

1 Approved Answer

Individual Risk plan and Individul EVM plan Project Budget Notes Hourly wage rates Project Manager (PM) hourly wage rate is $45/hr Company employee hourly wage

Individual Risk plan and Individul EVM plan

Project Budget Notes

Hourly wage rates

Project Manager (PM) hourly wage rate is $45/hr

Company employee hourly wage rate is $22/hr

Material Quotes

Cabinets $8,343

Sink/faucet $1,070

Appliances $3,095

Paint $760

Granite countertop $3,100

Tile materials $1,350

Work package

Duration (days)

Notes

1.1

Demolition: remove all old appliances, cabinets, and flooring

3

PM works 1 hour on day 1

(2) employees each work 8 hours on day 1

(1) employee works 8 hours on day 2

1.2

Haul away materials/debris

1

(2) employees each work 4 hours

2.1

Order cabinets

2

PM works 2 hours on day 1 (measuring)

PM works 2 hours on day 2 (ordering/paying for material)

2.2

Order sink/faucet

1

PM works 1 hour (ordering/paying for material)

2.3

Order appliances

1

PM works 1 hour (ordering/paying for material)

2.4

Order paint

2

PM works 1 hour (ordering/paying for material)

3.1

Create countertop subcontract

1

PM works 2 hours (ordering material)

Subcontractor requires 50% deposit on countertop material cost

3.2

Create tile subcontract

3

PM works 2 hours on day 1 (planning layout)

PM works 2 hours on day 2 (meeting subcontractor)

3.3

Create painting subcontract

1

PM works 1 hour (meeting subcontractor)

4.1

Install cabinets

3

PM works 1 hour on day 1

(2) employees each work 6 hours on days 1 and 2

(1) employee works 6 hours on day 3

PM works 1 hour on day 3

4.2

Install countertop

1

Subcontractor charges $350 for labor

Subcontractor collects remaining 50% countertop material cost

4.3

Install tile floors

4

Subcontractor charges $1100 for labor

Subcontractor collects tile material cost

4.4

Install sink/faucet

1

(1) employee works 8 hours

4.5

Install appliances

2

(2) employees each work 8 hours on days 1 and 2

5.1

Paint walls & ceiling

4

Subcontractor charges $1600 for labor

6.1

PM Inspection/punchlist

3

PM works 2 hours

(1) employee works 4 hours

6.2

Walk through / acceptance

1

PM works 1 hour

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Public Finance and Public Policy

Authors: Jonathan Gruber

4th edition

1429278455, 978-1429278454

More Books

Students also viewed these Finance questions