Instant Dolls specialises in manufacturing dolls. Their business process consists of the following activities, which must be conducted in the sequence described below ( The

Instant Dolls specialises in manufacturing dolls. Their business process consists of the following activities, which must be conducted in the sequence described below (The time required for each activity is shown in parenthesis):
Activity 1: Get the specifications of the doll from the customer, get the payment and submit the order to the production line. (6 minutes)
Activity 2: Assemble the main body of the doll. (12 minutes)
Activity 3: Add hair and paint. (12 minutes)
Activity 4: Dress the doll. (3 minutes)
Activity 5: Package the doll. (7 minutes)
The whole process is conducted by three workers. The assignment of tasks to workers is the following:
Worker 1 does Activity 1;
Worker 2 does Activities 2 and 3;
Worker 3 does Activities 4 and 5.
What is the utilisation rate of Worker 3? Express your answer as a % to 2 decimal places.
NOTE: there are no buffers between the stations.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Project Management

Authors: Jack Gido, Jim Clements

4th Edition

9780324656152, 324656130, 978-0324656138

More Books

Students also viewed these General Management questions