Question
Integrative: Complete investment decisionWith the market price of gold at C$1,562.50 per ounce (C$ stands for Canadian dollars), Maritime Resources Corp., a Canadian mining firm,
|
Integrative: Complete investment decisionWith the market price of gold at
C$1,562.50
per ounce (C$ stands for Canadian dollars), Maritime Resources Corp., a Canadian mining firm, would like to assess the financial feasibility of reopening an old gold mine that had ceased operations in the past due to low gold prices. Reopening the mine would require an up-front capital expenditure of
C$68.1
million and annual operating expenses of
C$19.41
million. Maritime expects that over a 5-year operating life it can recover
173,000
ounces of gold from the mine and that the project will have no terminal value. Maritime uses straight-line depreciation, has a
22.46%
corporate tax rate, and has a(n)
11.1%
cost of capital. Before moving forward with the project, Maritime would like to determine the sensitivity of its capital budgeting decision to the market price of gold, which could fluctuate over the 5-year period.a. Calculate the internal rate of return (IRR) for the gold mine project if the price of gold drops
10%.
b. Calculate the net present value (NPV) for the gold mine project if the price of gold drops
10%.
c. Calculate the internal rate of return (IRR) for the gold mine project if the price of gold drops
20%.
d. Calculate the net present value (NPV) for the gold mine project if the price of gold drops
20%.
e. Below what price per ounce of gold is Maritime's reopening of its old mine no longer acceptable?
a. If the price of gold drops
10%,
the internal rate of return (IRR) for the gold mine project is
nothing%.
(Round to two decimal places.)b. If the price of gold drops
10%,
the net present value (NPV) for the gold mine project is
$nothing.
(Round to the nearest cent.)c. If the price of gold drops
20%,
the internal rate of return (IRR) for the gold mine project is
nothing%.
(Round to two decimal places.)d. If the price of gold drops
20%,
the net present value (NPV) for the gold mine project is
$nothing.
(Round to the nearest cent.)e. Maritime's reopening of its old mine no longer acceptable once the price per ounce of gold is
$nothing.
(Round to the nearest cent.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started