Interim Quality Performance Report Davis, Inc., had the following quality costs for the years ended December 31, 20x4 and 20x5: 20x4 20x5 Prevention costs: Quality

Interim Quality Performance Report

Davis, Inc., had the following quality costs for the years ended December 31, 20x4 and 20x5:

20x4 20x5
Prevention costs:
Quality audits $66,000 $99,000
Vendor certification 121,500 182,250
Appraisal costs:
Product acceptance $90,000 $135,000
Process acceptance 87,000 102,500
Internal failure costs:
Retesting $100,000 $94,000
Rework 200,000 170,000
External failure costs:
Recalls $145,000 $116,000
Warranty 315,000 318,000

At the end of 20x4, management decided to increase its investment in control costs by 50 percent for each categorys items with the expectation that failure costs would decrease by 20 percent for each item of the failure categories. Sales were $12,500,000 for both 20x4 and 20x5.

Required:

1. Calculate the budgeted costs for 20x5.

$

Prepare an interim quality performance report. Enter all answers as positive amounts. If there is no variance enter "0" for your answer. If the budget variance amount is unfavorable select "Unfavorable" in the last column of the table, select "Favorable" if it is favorable, or No effect if there is no change. Round percentage answers to two decimal places. For example, 5.789% would be entered as "5.79".

Davis, Inc.
Interim Standard Performance Report: Quality Costs
For the Year Ended December 31, 20x5
Actual Costs Budgeted Costs Variance Unfavorable, Favorable or No effect
Prevention costs:
$ $
Total prevention costs $ $
Appraisal costs:
$ $
$
Total appraisal costs $ $ $
Internal failure costs:
$ $ $
Total internal failure costs $ $ $
External failure costs:
$ $
Total external failure costs $ $ $
Total quality costs $ $ $
Percentage of sales % % %

2. What can be inferred from the report regarding the progress Davis has made?

Davis has not come close to meeting the planned outcomes

Davis has come very close to meeting the planned outcomes

OR

Davis has exceeded the planned outcomes

3. What if sales were $12,500,000 for 20x4 and $15,625,000 for 20x5? What adjustment to budgeted rework costs would be made? (Note: Quality auditing is a discretionary cost and its budget is not affected by the change in sales revenue in 20x5.)

New total budgeted rework costs: $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Peter Brewer, Ray Garrison, Eric Noreen, Suresh Kalagnanam, Ganesh Vaidyanathan

5th Edition

1259256081, 978-1259256080

More Books

Students also viewed these Accounting questions

Question

=+3. What are their performance levels?

Answered: 1 week ago

Question

=+j Describe the various support services delivered by IHR.

Answered: 1 week ago

Question

=+j Explain IHRMs role in global HR research.

Answered: 1 week ago