Investment and Corresponding Returns Scenario Probability Project A Project B Project C Project D Pessimistic 50% -8% -5% -7% 0% Normal 40% 0 1% -2%
Investment and Corresponding Returns | |||||
Scenario | Probability | Project A | Project B | Project C | Project D |
Pessimistic | 50% | -8% | -5% | -7% | 0% |
Normal | 40% | 0 | 1% | -2% | 1% |
Optimistic | 10% | 5% | 3% | 6% | 2% |
what is the standard deviation?
with the values of Expected Return for Project A -3.50%
Expected Return for Project B -1.80%
Expected Return for Project C -3.70%
Expected Return for Project D 0.60%
Step by Step Solution
There are 3 Steps involved in it
Step: 1