Iron Corporation is constructing an office building under contract for Coal Corp. The contract calls for progress billing and payments of $620,000 each quarter. The

Iron Corporation is constructing an office building under contract for Coal Corp. The contract calls for progress billing and payments of $620,000 each quarter. The total contract price is $7,440,000 and from Corporation estimates total cost of $7,100,000. Iron Corporation estimates that the building will take three years to complete, and commence construction on Jan. 2nd , 2010.

At December, 31 2010, Iron Corp. estimates that it is 30% complete with the construction, based on costs incurred. What is the total amount of Revenue from Long-Term contracts recognized fro 2010?

What is the second number in the value of the revenue that should be recognized (2010)?

Revenue (not Gross Profit) (to be recognized) => second number

A) number => 0 or 1

B) number => 2 or 3

C) number => 4 or 5

D) number => 6 or 7

E) number => 8 or 9

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Information And Cyber Security Governance

Authors: Robert E Davis

1st Edition

1000416089, 9781000416084

More Books

Students also viewed these Accounting questions

Question

LO.3 Identify the adjustments made in calculating the AMT.

Answered: 1 week ago