is responsible for determining the capacity required and with methods of making the capacity available. ( 2 . 5 pts ) a . Production planning
is responsible for determining the capacity required and with methods of making the capacity available. pts
a Production planning
b Master production scheduling
c Production activity control
d Capacity planning
e Material requirements planning
Rated capacity is calculated taking into account work center and pts
I. historical data
II utilization
III. efficiency
a I and II
b I and III
c II and III
d none of the above
A work center has machines and is operated for hours a day, days a week. What is the availab time? pts
a hours
b hours
c hours
d hours
e hours
Information on the standard times for an operation will be found in: pts
a the work center file
b the routing file
c the master file
d the product file
e the production file
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started