Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

is the objective function cost calculated per hour or day? 15 and 10 are the cost for 1 hr work for FTE and PTE so

is the objective function cost calculated per hour or day? 15 and 10 are the cost for 1 hr work for FTE and PTE so not sure why for PTE we multiplied by 2

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these General Management questions

Question

By what criteria may secondary data be evaluated?

Answered: 1 week ago