It is week 35 of a busy year at Ashby Architects and Jo Ashby is facing a big problem. Both her two junior partners have
It is week 35 of a busy year at Ashby Architects and Jo Ashby is facing a big problem. Both her two junior partners have been diagnosed with a serious illness contracted on a trip to scope out a prospective job in Lichenstein. So jo has to step in and complete the outstanding jobs that were being worked on by two juniors. The outstanding jobs are shown in table 10.7.
Jo has heard that a sequencing rule called the critical ratio (CR) will give efficient results. The priority of jobs using the CR rule is defined by an index computed as follow:
CR = time remaining/workdays remaining = (due date - todays date) / workdays remaining
Outstandnig jiobs that jop needs to complete:
Job | Due Date (work) | Weeks of work remaining |
Ashthorpe lavatory block | 40 | 2.0 |
Bubgwitch bus shelter | 48 | 5.0 |
Crudstone plc HQ | 51 | 3.0 |
Dredge sewage works | 52 | 8.0 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started