Question
Item 11 Fortes Incorporated has provided the following data concerning one of the products in its standard cost system. Variable manufacturing overhead is applied to
Item 11
Fortes Incorporated has provided the following data concerning one of the products in its standard cost system. Variable manufacturing overhead is applied to products on the basis of direct labor-hours.
Inputs | Standard Quantity or Hours per Unit of Output | Standard Price or Rate | ||
---|---|---|---|---|
Direct materials | 8.1 | ounces | $ 6.20 | per ounce |
Direct labor | 0.6 | hours | $ 20.80 | per hour |
Variable manufacturing overhead | 0.6 | hours | $ 4.50 | per hour |
The company has reported the following actual results for the product for April:
Actual output | 5,700 | units |
---|---|---|
Raw materials purchased | 48,300 | ounces |
Actual cost of raw materials purchased | $ 280,560 | |
Raw materials used in production | 46,200 | ounces |
Actual direct labor-hours | 3,160 | hours |
Actual direct labor cost | $ 68,850 | |
Actual variable overhead cost | $ 13,405 |
Required:
a. Compute the materials price variance for April.
b. Compute the materials quantity variance for April.
c. Compute the labor rate variance for April.
d. Compute the labor efficiency variance for April.
e. Compute the variable overhead rate variance for April.
f. Compute the variable overhead efficiency variance for April.
(Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.)
Fortes Incorporated has provided the following data concerning one of the products in its standard cost system. Variable manufacturing overhead is applied to products on the basis of direct labor-hours. Inputs Direct materials Direct labor Variable manufacturing overhead Standard Quantity or Hours per Unit of Output 8.1 ounces 0.6 hours 0.6 hours Standard Price or Rate $ 6.20 per ounce $ 20.80 per hour $ 4.50 per hour The company has reported the following actual results for the product for April: Actual output Raw materials purchased Actual cost of raw materials purchased Raw materials used in production Actual direct labor-hours Actual direct labor cost Actual variable overhead cost 5,700 units 48, 300 ounces $ 280,560 46,200 ounces 3,160 hours $ 68,850 $ 13, 405 Required: a. Compute the materials price variance for April. b. Compute the materials quantity variance for April. c. Compute the labor rate variance for April. d. Compute the labor efficiency variance for April. e. Compute the variable overhead rate variance for April. f. Compute the variable overhead efficiency variance for April. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) a. Materials price variance b. Materials quantity variance c. Labor rate variance d. Labor efficiency variance e. Variable overhead rate variance f. Variable overhead efficiency variance
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started