Item 2 3 3 . 4 4 points Return to questionItem 2 3 EX 9 - 2 ( Static ) Use the information contained below...

Item23
3.44
points
Return to questionItem 23
EX9-2(Static) Use the information contained below...
Use the information contained below to compress one-time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(s) was crashed and the adjusted total cost.
Activity Crash cost Maximum
ID (Slope) Crash Time Normal time Normal cost
A 02150
B 10013100
C 5026200
D 4014200
E 5513200
F 01150
Total direct normal costs $1,000
To compress from time period 13 to time 12 crash the following activity(s)(You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.)
check all that apply 1
Aunanswered
Bunanswered
Cunanswered
Dunanswered
Eunanswered
Funanswered
To compress from time period 12 to time 11 crash the following activity(s)(You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.)
check all that apply 2
Aunanswered
Bunanswered
Cunanswered
Dunanswered
Eunanswered
Funanswered
To compress from time period 11 to time 10 crash the following activity(s)(You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.)
check all that apply 3
Aunanswered
Bunanswered
Cunanswered
Dunanswered
Eunanswered
Funanswered
What is the crash point of the network?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

12th Edition

840062338, 840062346, 9780840062338, 978-0840062345

More Books

Students also viewed these General Management questions