ITPM Each box is an activity, the number it contains is the duration of the activity in days. The duration of the critical path is:
ITPM
Each box is an activity, the number it contains is the duration of the activity in days. The duration of the critical path is: 2 2. 3 6 2 Select one: O a. 14 O b. 16 O c. 15 O d. 20 A change control system should be created : Select one: .a. as needed on the project team b. No need to create formal document, O c. as a formal documented procedure d. as needed on the project