Question
Ivanhoe Company was organized on January 1. During the first year of operations, the following plant asset expenditures and receipts were recorded in random order.
Ivanhoe Company was organized on January 1. During the first year of operations, the following plant asset expenditures and receipts were recorded in random order.
Debit
1.Excavation costs for new building $13,545
2.Architect's fees on building plans 41,540
3.Full payment to building contractor 667,100
4.Cost of real estate purchased as a plant site (land $285,200and building $32,700) 317,900
5.Cost of parking lots and driveways 37,530
6.Accrued real estate taxes paid at time of purchase of real estate 3,710
7.Installation cost of fences around property 6,240
8.Cost of demolishing building to make land suitable for construction of new building 31,700
9.Real estate taxes paid for the current year on land 6,790
$1,126,055
Credit
10.Proceeds from salvage of demolished building$12,800
Analyze the transactions by placing each item and its amount in its designated Land, Building, or Other Account column. If it falls into other account, indicate the account title, (ex. prepaid insurance, license expense, etc.) Enter the amounts in the appropriate columns.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started