J | K ( 1 ) 4 ( 4 ) IM ( 2 ) . . 1 4 . 2 You are expected to have
J K IM You are expected to have the gift bags in Problem ready at PM However, you need to personalize the items monogrammed pens, note pads, literature from the printer, etc. The lead time is hour to assemble Js once the other items are prepared. The other items will take a while as well. Given the volunteers you have, the other time estimates are item K hours item L hour and item M hours
Step by Step Solution
There are 3 Steps involved in it
Step: 1