JB's small engine production facility operates three eight hour shifts per day, five days per week. Their effective capacity is 225 units per hour. Last
JB's small engine production facility operates three eight hour shifts per day, five days per week. Their effective capacity is 225 units per hour. Last week they produced 23247 units. What was their