Jefferson Blush Manufacturing Inc. (the company) has three different categories of overhead. The overhead costs for each of the categories for the next year are
Jefferson Blush Manufacturing Inc. ("the company") has three different categories of overhead.
The overhead costs for each of the categories for the next year are as follows:
Costs | Cost Driver | Expected Activity | |
Materials handling | $360,000 | Material moves | 18,000 |
Maintenance | $550,000 | Machine hours | 55,000 |
Inspection | $30,000 | Inspections | 10,000 |
Currently, the company applies overhead using a plantwide predetermined overhead rate based upon a budgeted direct labour hours of 80,000.
The company has been asked to submit a bid on a proposed job.
In order to submit this bid, the company needs to calculate the total cost of performing this job.
Financial details for the proposed job are as follows:
Direct materials | $55,000 |
Direct labour | $45,000 |
Number of direct labour hours | 15,000 |
Number of material moves | 50 |
Number of inspections | 180 |
Number of machine hours | 3,000 |
Use the information provided to answer the following questions.
PART A:
Assume the company is exploring the use of activity based costing.
If the company used activity-based costing, the total overhead cost that would be assigned to the job for material handling is $_______________.
If the company used activity-based costing, the total overhead cost that would be assigned to the job for maintenance is $___________.
If the company used activity-based costing, the total overhead cost that would be assigned to the job for inspections is $______________.
If the company used activity-based costing, the total material costs plus the total direct labour costs assigned to the job would be $___________.
If the company used activity-based costing, the total cost of the job would be $__________.
PART B:
Assume, instead, that the company continues to use the plantwide overhead application rate.
If the company allocated overhead to the job using a plantwide overhead rate, the total overhead cost assigned to the job would be $_____________.
If the company allocated overhead to the job using a plantwide overhead rate, the total cost of the job would be $__________.
PART C:
If the company decided to continue to use the plantwide overhead application rate, which of the following statements is true?
Enter either A or B in the space provided.
A. Use of the plantwide rate would cause the company to over-price the job.
B. Use of the plantwide rate would cause the company to under-price the job.
Part D:
Read the following statement and indicate if the statement is TRUE (enter T) or FALSE (enter F).
It would be appropriate to adopt an ABC policy if the company produced multiple products and the products were quite similar.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started