Jellybean Flavor Labs makes the cherry flavor for a famous jelly bean and uses a standard costing system. They have provided the following standard information:
Jellybean Flavor Labs makes the cherry flavor for a famous jelly bean and uses a standard costing system. They have provided the following standard information:
Direct materials: 2.5 ounces at $20 per ounce
Direct labor: 1.4 hours at $12.50 per hour
Variable manufacturing overhead: 1.4 hours at 3.50 per hour
Variable manufacturing overhead is applied on the basis of standard direct labor-hours. The following data are available for December:
- 3,750 units of compound were produced during the month.
- There was no beginning direct materials inventory.
- Direct materials purchased: 12,000 ounces for $225,000.
- The ending direct materials inventory was 2,000 ounces.
- Direct labor-hours worked: 5,600 hours at a cost of $67,200.
- Variable manufacturing overhead costs incurred amounted to $18,200.
- Variable manufacturing overhead applied to products: $18,375.
The materials price variance for December is:
Question 17 options:
| $15,000 Unfavorable |
| $15,000 Favorable |
| $25,000 Unfavorable |
| $25,000 Favorable |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started