JJ Abrams planned to use $164 of material per unit but actually used $160 of material per unit, and planned to make 1,200 units but
- JJ Abrams planned to use $164 of material per unit but actually used $160 of material per unit, and planned to make 1,200 units but actually made 1,000 units.
-
A) The flexible-budget amount is:
$160,000 $164,000 $192,000 $196,800
B) The flexible-budget variance is:
$4,000 favorable
| ||
$28,000 unfavorable
| ||
$32,800 unfavorable
| ||
$4,800 favorable |
C) The sales-volume variance is:
$4,000 favorable
| ||
$28,000 unfavorable
| ||
$32,800 favorable
| ||
$4,800 favorable
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started