Job 7890 was recently completed. The following data have been recorded on its job cost sheet: Direct materials$45,000 Direct labor-hours 630labor-hours Direct labor wage rate$13per

Job 7890 was recently completed. The following data have been recorded on its job cost sheet:
Direct materials$45,000
Direct labor-hours 630labor-hours
Direct labor wage rate$13per labor-hour
Machine-hours 390machine-hours
Number of units completed 3,000units
The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $12 per machine-hour.
Required:
Compute the unit product cost that would appear on the job cost sheet for Job 7890.
image text in transcribed
2) Job 7890 was recently completed. The following data have been recorded on its job cost sheet: Direct materials 45,000 Direct labor-hours 630 labor-hours Direct labor wage rate Machine-hours Number of units completed The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $12 per machine-hour Required: Compute the unit product cost that would appear on the job cost sheet for Job 7890 per labor-hour machine-hours $ 13 390 3,000 units

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions