Job A,B,C,D,E has processing times (days): 8,2,4,6,7 and immediate predecessors are ,A,B,B, and C&D, respectively. What is the earliest starting time of C ? a.
Job A,B,C,D,E has processing times (days): 8,2,4,6,7 and immediate predecessors are ,A,B,B, and C&D, respectively. What is the earliest starting time of C ? a. 14 b. 10 c. 16 d. 11