Joe used a project management software package and has determined the following results for a given project: Expected completion time of results of project=22 days

Joe used a project management software package and has determined the following results for a given project:

Expected completion time of results of project=22 days

Variance of project of completion time = 2.77

What is the probability of completing the project within 20 days?

0.3849

0.8849

0.1151

0.7642

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to graph theory

Authors: Douglas B. West

2nd edition

131437372, 978-0131437371

More Books

Students also viewed these Mathematics questions