John worked as a project manager for ucertify inc. He's working on a project and has just contacted the application team for an estimate on
John worked as a project manager for ucertify inc. He's working on a project and has just contacted the application team for an estimate on their assignment the application team notified that the most likely estimate of completion is 29 days the pessimistic estimate is 38 days and the optimistic estimate is 15 days what is the PERT estimate of the assignments A. 28 B. 39 C. 13 D. 21