Question
Johnson Electronics manufactures a power supply used in a variety of electronics products, including printers, modems, and routers. The demand for the part is 7,600
Johnson Electronics manufactures a power supply used in a variety of electronics products, including printers, modems, and routers. The demand for the part is 7,600 units per week. The production of the power supply requires six different manufacturing operations, each in sequence and each having the following processing times. The net available time to work is 54 hours per week, using two shifts.
OperationProcessing Time
(seconds)Operation 123Operation 220Operation 326Operation 422Operation 529Operation 624
Required:
1. What is the Takt time, in seconds, for this product?(Round your final answer to the nearest whole number.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started