JRE2 Incorporated entered into a contract to install a pipeline for a fixed price of $2,425,000. JRE2 recognizes revenue upon contract completion. Cost incurred Estimated
JRE2 Incorporated entered into a contract to install a pipeline for a fixed price of $2,425,000. JRE2 recognizes revenue upon contract completion.
Cost incurred | Estimated Cost to Complete | |
---|---|---|
2023 | $ 280,000 | $ 1,700,000 |
2024 | 1,750,000 | 650,000 |
2025 | 600,000 | 0 |
In 2024, JRE2 would report gross profit (loss) of: