K Goddard Inc. planned to use $157 of material per unit but actually used $148 of material per unit, and planned to make 1,160
K Goddard Inc. planned to use $157 of material per unit but actually used $148 of material per unit, and planned to make 1,160 units but actually made 1,000 units The flexible-budget amount for materials is OA. $171,680 OB. $182,120 Oc. $157,000 D. $148,000