Question
1 Approved Answer
KINDLY READ THE QUESTION CAREFULLY AND PLEASE TRY TO SOLVE WHATEVER PART IS HIGHLIGHTED IN THE GIVEN QUESTION AS EACH PART CARRIES EQUAL IMPORTANCE. A
KINDLY READ THE QUESTION CAREFULLY AND PLEASE TRY TO SOLVE WHATEVER PART IS HIGHLIGHTED IN THE GIVEN QUESTION AS EACH PART CARRIES EQUAL IMPORTANCE.
A hydroelectric power station with firm capacity of 100 MW must be constructed on a site where head of water is expected to be 150 meters. Compute the required water flow rate in cumecs which ensures that the plant gives the rated output if the efficiency of this plant is expected to be 85%. Compute the volume of pondage required to ensure adequate water discharge for production of the rated power from the given monthly discharge of this site in table 1 (assume the average length of a month to be 30.42 days). Table 1: Monthly Discharge Data for Question 2 Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Discharge 55 45 75 85 00 110 120 90 80 (m/sec) A hydroelectric power station with firm capacity of 100 MW must be constructed on a site where head of water is expected to be 150 meters. Compute the required water flow rate in cumecs which ensures that the plant gives the rated output if the efficiency of this plant is expected to be 85%. Compute the volume of pondage required to ensure adequate water discharge for production of the rated power from the given monthly discharge of this site in table 1 (assume the average length of a month to be 30.42 days). Table 1: Monthly Discharge Data for Question 2 Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Discharge 55 45 75 85 00 110 120 90 80 (m/sec)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started