King Towels spends 48 minutes per order on non-value-added activities. The total manufacturing cycle time is 120 minutes per order. What is the manufacturing cycle
King Towels spends 48 minutes per order on non-value-added activities. The total manufacturing cycle time is 120 minutes per order. What is the manufacturing cycle efficiency?
A : 36.67% B : 66.67% C : 60% D : 40%