Kingbird Construction Company began work on a $420,300 construction contract in 2017. During 2017, Kingbird incurred costs of $280,600, billed its customer for $213,900, and
Kingbird Construction Company began work on a $420,300 construction contract in 2017. During 2017, Kingbird incurred costs of $280,600, billed its customer for $213,900, and collected $173,600. At December 31, 2017, the estimated additional costs to complete the project total $163,000.
Prepare Archers journal entry to record profit or loss using (a) the percentage-of-completion method and (b) the completed-contract method, if any. (Credit account titles are automatically indented when amount is entered. Do not indent manually. Round percentage value to 2 decimal places, e.g. 52.15% and final answers to 0 decimal places, e.g. 1525.)
a) Dr. Construction Expenses
Cr. Construction in Process
Cr. Revenue from Long Term Contracts
b) Dr. Loss from Long Term Contracts
Cr. Construction in Process
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started