Koser Corporation expects to use 2 hours per unit to make its product. During April, it actually made 8,000 units. The company recorded a labor

Koser Corporation expects to use 2 hours per unit to make its product. During April, it actually made 8,000 units. The company recorded a labor rate variance of $12,000 U and a labor efficiency variance of $7,200 for April. Koser expects to compensate its employees at an average rate of $25 per hour.

What is the total actual cost of the direct labor?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

First we calculated the Actual Hours as 16288 hours Now you can find the total actu... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost management a strategic approach

Authors: Edward J. Blocher, David E. Stout, Gary Cokins

5th edition

73526940, 978-0073526942

More Books

Students also viewed these Accounting questions

Question

What is marketing research? AppendixLO1

Answered: 1 week ago

Question

Describe the flow of costs through a job costing system.

Answered: 1 week ago