LaCrosse, Inc., sales manager Josh Brown has been receiving calls from customers complaining about the length of time it takes to receive an order. To

LaCrosse, Inc., sales manager Josh Brown has been receiving calls from customers complaining about the length of time it takes to receive an order. To help him understand the issue, he gathered the following information from DanGold Enterprises most recent order.

Days Required
Process customer order 0.1
Wait for direct materials to arrive 2.0
Fabrication of parts 3.0
Move order to assembly department 0.5
Wait for machine time 6.5
Assembly of parts 4.0
Move order to finishing department 0.3
Wait for machine time 3.0
Finishing of units 5.0
Move to packing department 0.7
Packing 1.6
Move to shipping department 0.3
Load delivery truck 0.7
Drive to customer 1.5
Unload delivery truck 0.9
Return to plant

1.0

a.) Calculate the delivery cycle time for DanGolds order. (Round answer to 1 decimal place, e.g. 12.5.)

Delivery Cycle Time ____ Days

b. ) Calculate the manufacturing cycle time for DanGolds order

Manufacturing Cycle time ___ days

c.) Calculate the value-added time for DanGolds order

Value added time ____ days

d.) alculate the manufacturing cycle efficiency for DanGolds order.

Manufacturing cycle effiency ___ days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Frank Woods Business Accounting Volume 2

Authors: Frank Wood, Alan Sangster

13th Edition

1292085053, 9781292085050

More Books

Students also viewed these Accounting questions