LaCrosse, Inc., sales manager Josh Brown has been receiving calls from customers complaining about the length of time it takes to receive an order. To
LaCrosse, Inc., sales manager Josh Brown has been receiving calls from customers complaining about the length of time it takes to receive an order. To help him understand the issue, he gathered the following information from DanGold Enterprises most recent order.
Days Required | |||||
Process customer order | 0.1 | ||||
Wait for direct materials to arrive | 2.0 | ||||
Fabrication of parts | 3.0 | ||||
Move order to assembly department | 0.5 | ||||
Wait for machine time | 6.5 | ||||
Assembly of parts | 4.0 | ||||
Move order to finishing department | 0.3 | ||||
Wait for machine time | 3.0 | ||||
Finishing of units | 5.0 | ||||
Move to packing department | 0.7 | ||||
Packing | 1.6 | ||||
Move to shipping department | 0.3 | ||||
Load delivery truck | 0.7 | ||||
Drive to customer | 1.5 | ||||
Unload delivery truck | 0.9 | ||||
Return to plant | 1.0 |
a.) Calculate the delivery cycle time for DanGolds order. (Round answer to 1 decimal place, e.g. 12.5.) | |||
Delivery Cycle Time ____ Days
| |||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started