Lee - Anne is the project manager of a web development team that has been tasked with building a new website for a client. Neither
LeeAnne is the project manager of a web development team that has been tasked with building a new website for a client. Neither the graphic designing nor the copywriting can start until the site architecture is signed off by the client. If architecture signoff is task Asite copywriting is task B and design images is task C what would be the sequence of dependencies between these three tasks?
Question Select one:
a
A to B is finish to start; A to C is finish to start
b
A to B is finish to start; B to C is start to start
c
A to B is finish to start; B to C is finish to start
d
A to B is start to start; A to C is start to start
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started