Leon Company s city center plant recently hired a second shift of employees who manufacture the product Plumbo. ( The second shift works from 4
Leon Companys city center plant recently hired a second shift of employees who manufacture the product Plumbo. The second shift works from pm to midnight after the first shift is finished, which doubles the total plant capacity. Information about the cost of labour in the previous month is as follows:
Standard
Actual units produced
Hours
hrsunit
hours
Rate
$hr
$
The labour rate variance at the city centre plant in the previous month was: